We were actually on site with my hubby's father and brother-in-law to move the leftover bricks (about 1.5 pallets) and I was surprised to see a van out front and doors and windows open. A tradie was there installing kitchen shelves and sliding doors for the wardrobes.
Here are the sliding mirror doors for the wardrobes in bedroom 2, 3 and 4.
Also on Friday the Ultra Air guys came around to install the intake duct and outlet covers. I didn't see any controllers - they're marked on our electrical plan - perhaps they come back and do them later. We are supposed to have a controller upstairs and downstairs.
The a/c outlet - ignore the fan blade - they were installed by accident!
The door frames and doors themselves had also been painted on Friday - but not the walls yet. I think that's on the card for next week.

Congrats on the weekend work - we had the painters at ours redoing a few areas and painting our downpipes etc that were only just fitted.
ReplyDeleteI think you have caught back up to us now - possibly even passed us as we havent received our splashback or driveway form work yet!